Toktogul water reservoir to be full by August 2017
According to preliminary data of Kyrgyzhydromet, the inflow in 2017 will amount to 124 percent. In
According to Electric Stations JSC, it is planned to export electricity. During the heating period of 2017–2018, the Bishkek Heating and Power Plant will operate only according to the heating schedule.
At this time, two new units of the heating plant will be put into operation. The electrical load during the operation of these units in the forthcoming
To reduce the cost of fuel, the boilers will work using Shubarkul coal without the use of natural gas or fuel oil.
If they are switched to local coal, it is necessary to additionally burn natural gas or heating oil for stable operation and carrying the given loads. At least