Cost of unforeseen work on North-South road reaches $ 55 million
The cost of additional and unforeseen works within the first phase of construction of
As reported, after the construction of the technological road and approaches to the portals on both sides of the tunnel, an additional topographic survey of the area, where the route will run, and hydrogeological surveys were carried out.
Based on the results obtained, a detailed design for
The Ministry of Transport and the Ministry of Finance were instructed to raise additional funds, negotiations with various organizations, where the
In the first phase of the construction of the alternative
In the second phase, which was started in 2016, about 22 percent of the contract amount was disbursed, the statement said.