17:46, 12 июня 2017, 24.kg

Repair of Tash-Kumyr hydropower station to cost 102 million soms

Repair of Tash-Kumyr hydropower station to cost 102 million soms, the chief engineer of the hydroelectric power plant Taalaibek Bektenov said during a press tour to energy facilities in Jalal-Abad region.

According to him, the funds will be spent on installation, electrical and finishing work.

As he noted, the company «Narynhydroenergostroy», which won a tender for contract work, produces granite floors, wall cladding and other finishing works.

In addition, according to the chief engineer, in 2017, It is planned to replace the excitation system of one of the hydro-power plant units at Tash-Kumyr hydropower plant. «Some equipment is more than 30 years old, and the time of its modernization has already come," he said.

According to Taalaibek Bektenov, the tender for replacement of the equipment was won by the Russian company.

Views
562
Views
Views
Views
Жизнь за рубежом. Истории кыргызстанцев
Происшествия
Власть
Атака на Иран
Экономика

КОНТАКТЫ

СОЦСЕТИ

TelegramYouTubeWhatsAppFacebookInstagram

© ИА «24.kg» - Новости Кыргызстана. Все права защищены. Вся информация, размещенная на данном веб-сайте, предназначена только для персонального использования и не подлежит распространению без письменного разрешения ИА «24.kg». Редакция не несет ответственности за содержимое перепечатанных материалов и высказывания отдельных лиц. +18