Repair of HPP in Kyrgyzstan drags on due to conflict among tender participants
The repair of the hydropower plants in
The company told that a tender for a total cost of 43.5 million soms was announced for the repair of equipment at Toktogul, Shamaldysay, Uch-Kurgan, At-Bashi HPPs.
Applications were submitted by three companies. The lowest cost was offered by the Russian company Hydroremont VKK. It intended to attract a subcontractor, but the latter did not meet the requirements. In this connection, the tender commission rejected the application and awarded the victory to the next company — Narynspetsgidroenergomontazh OJSC.
Since May 29, procurement procedures have been suspended as Narynspetsgidroenergomontazh filed a counter-claim to an independent commission. However, by law, its decision can be appealed only in court.
At the same time, the energy specialists note that the repairs were to start in May.