10:33, 18 апреля 2017, 24.kg

Mud flow in Suzak district damages power transmission line

Mud flow damaged high-voltage power transmission line of 110 kV Raionnaya — Urumbash in Suzak district of Kyrgyzstan. Press service of National Electric Network of the Kyrgyz Republic JSC reported.

It is noted that the support No. 91 of Raionnaya — Urumbassh line was damaged tonight in the village of Kara-Cholok. Consumers were promptly connected to the electricity under the reserve scheme, there are no disconnected users in Jalal-Abadelektro JSC networks.

Currently, Raionnaya — Urumbash transmission line was removed out of service for repair. Despite the continuing heavy rain, NENK’s workers started emergency repair work.

Views
370
Views
Views
Views
Жизнь за рубежом. Истории кыргызстанцев
Происшествия
Власть
Атака на Иран
Экономика

КОНТАКТЫ

СОЦСЕТИ

TelegramYouTubeWhatsAppFacebookInstagram

© ИА «24.kg» - Новости Кыргызстана. Все права защищены. Вся информация, размещенная на данном веб-сайте, предназначена только для персонального использования и не подлежит распространению без письменного разрешения ИА «24.kg». Редакция не несет ответственности за содержимое перепечатанных материалов и высказывания отдельных лиц. +18