Overhaul of first hydroelectric unit completed at Alamudun-1 HPP

Overhaul of the first hydroelectric unit was completed at Alamudun-1 hydropower plant (HPP). Chakan HPP company reported.

The company noted that in preparation for the autumn-winter period, they continue to carry out repair work at their facilities.

Photo 300738

During the overhaul of the first unit, the specialists completely dismantled the equipment and replaced obsolete parts.

Chakan HPP company plans to start overhaul of the second hydroelectric unit in July.

Alamudun-1 HPP is the second stage of eight stations of the cascade of Alamudun HPPs. The station was put into operation in 1945. Its total capacity is 2.2 MW.

Views
0
Views
Views
Views
Жизнь за рубежом. Истории кыргызстанцев
Происшествия
Власть
Атака на Иран
Экономика

КОНТАКТЫ

СОЦСЕТИ

TelegramYouTubeWhatsAppFacebookInstagram

© ИА «24.kg» - Новости Кыргызстана. Все права защищены. Вся информация, размещенная на данном веб-сайте, предназначена только для персонального использования и не подлежит распространению без письменного разрешения ИА «24.kg». Редакция не несет ответственности за содержимое перепечатанных материалов и высказывания отдельных лиц. +18