1.5 billion soms allocated for construction of Kambarata HPP-1

A loan in the amount of 1.5 billion soms was allocated from the republican budget for the construction of Kambarata HPP-1. The Cabinet of Ministers confirmed the information to 24.kg news agency.

The recipient of the loan is Electric Stations OJSC. Kambarata HPP-1 is the largest power facility of the entire cascade.

The project provides for the construction of a rockfill dam 256 meters high and the station itself with an installed capacity of 1,860 megawatts. An average long-term electricity generation at the Kambarata HPP-1 will be 5.6 billion kilowatt-hours with a total reservoir capacity of 5.4 billion cubic meters of water.

The construction period is from 8 to 10 years. Commissioning of the first hydroelectric unit of the HPP is planned in four years, if there is permanent financing.

Views
0
Views
Views
Views
Жизнь за рубежом. Истории кыргызстанцев
Происшествия
Власть
Атака на Иран
Экономика

КОНТАКТЫ

СОЦСЕТИ

TelegramYouTubeWhatsAppFacebookInstagram

© ИА «24.kg» - Новости Кыргызстана. Все права защищены. Вся информация, размещенная на данном веб-сайте, предназначена только для персонального использования и не подлежит распространению без письменного разрешения ИА «24.kg». Редакция не несет ответственности за содержимое перепечатанных материалов и высказывания отдельных лиц. +18