Since the beginning of March, branches of district power networks of Bishkek, Chui and Talas regions have started annual scheduled repairs. Press service of Severelectro OJSC reported.

In order to improve reliability of power supply to consumers, trees will be trimmed along 46 kilometers of transmission lines in Alamedin district.

More than 71.1 kilometers of overhead power lines will be reconstructed in Baytik, Kashka-Suu, Leninskoye, Vinogradnoye, Vasilyevka, Oktyabrskoye, Mayevka, Prigorodnoye, Vostok, Alamudun villages using self-supporting insulated wires.

In addition, power engineers will install three additional transformer substations in Lebedinovka, Leninskoye and Chon-Tash villages, increase the capacity of 15 overloaded transformer substations in Vasilyevka, Konstantinovka, Oktyabrskoye, Leninskoye, Lebedinovka, Vostok, Prigorodnoye, and Mayevka villages.

Views
0
Views
Views
Views
Происшествия
Жизнь за рубежом. Истории кыргызстанцев
Власть
Атака на Иран
Экономика

КОНТАКТЫ

СОЦСЕТИ

TelegramYouTubeWhatsAppFacebookInstagram

© ИА «24.kg» - Новости Кыргызстана. Все права защищены. Вся информация, размещенная на данном веб-сайте, предназначена только для персонального использования и не подлежит распространению без письменного разрешения ИА «24.kg». Редакция не несет ответственности за содержимое перепечатанных материалов и высказывания отдельных лиц. +18