Land not used by investor for HPP construction to be returned to state

The Ministry of Energy of Kyrgyzstan seizes the allocated land from those, who received it for the construction of a mini-hydroelectric power station but did not do so. Minister Taalaibek Ibraev announced at a meeting of Parliament.

According to him, investors have to draw up a feasibility study for the project within three months after receiving the land plot, develop it within six months, and launch construction within nine months.

He also noted that the construction period for a mini-hydroelectric power station cannot exceed three years. If the investor does not meet these deadlines, the land will be seized.

Views
0
Views
Views
Views
Ситуация с ГСМ в Кыргызстане
Происшествия
Агент 024
Власть
Общество
Атака на Иран
Экономика
Спорт
Полезные советы

Падение рубля: мигранты теряют доходы, а импорт в Кыргызстан становится выгоднее

3 дня назад

Техноблог

Последствия масштабных лесных пожаров в Европе показали с высоты

Торговля
Ситуация вокруг Украины

КОНТАКТЫ

СОЦСЕТИ

TelegramYouTubeWhatsAppFacebookInstagram

© ИА «24.kg» - Новости Кыргызстана. Все права защищены. Вся информация, размещенная на данном веб-сайте, предназначена только для персонального использования и не подлежит распространению без письменного разрешения ИА «24.kg». Редакция не несет ответственности за содержимое перепечатанных материалов и высказывания отдельных лиц. +18